A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.

How should the project manager deal with this request?

  • A. Check the alternative resources available in the organization for the request.
  • B. Confirm that the budget and resources are available to execute the work request.
  • C. Evaluate the nature of the request and plan communication accordingly.
  • D. Submit a change request and allocate the budget and resources needed for execution.

dump답은 C라고 하는데요. 

 

제 선택은 D로 이미 끝난 프로젝이를 이어서 해달라고 하는 요청이니 CR을 진행해서 resource를 받을 수 있게 해야하는거 아닌가요 

첨부파일
2023-07-25

안녕하세요. ITPE입니다.

 

정답은 C가 맞아요.

C. 요청의 성격을 평가하고 그에 따라 커뮤니케이션을 계획합니다.

 

이유. 본문을 보세요. 예측적 개발이라는 내용이 있나요?

없죠? 왜 항상 CR을 쓴다(예측적 개발 모델)고 생각하세요?

 

하이브리드 문제이므로, 내용을 보고, 결정한다가 답입니다. 따라서 C에요~

 

이번 2023년형 PMP 동영상 5일 수강 기간이면, 무료 요청하세요. 

기존 패키지 결제한 분들은 요청하면, 해당 기간 동안 +1로 무료로 드리니, 요청해서, 다시 한번 수강하세요.

 

PM님~ 이정도는 맞춰야 합니다.