덤프문제 질문(5) 드립니다.
오*수
|
2023-09-15

덤프문제입니다.

An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed. The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty.

 

What should the project manager do to mitigate this risk?

 

A. Review the issue with the project sponsor and ask for more time to complete this requirement.

B. Complete an impact analysis as the scope of the sprint backlog cannot be changed after the sprint has started.

C. Include the compliance user story in the next sprint as the team is fully occupied with the current sprint.

D. Request the team to add the user story to the current sprint and let them work on it.

 

 

민첩한 팀이 비즈니스 가치를 제공하기 위해 2주간의 스프린트를 진행하고 있습니다스프린트가 시작된 지 약 일주일 후제품 소유자는 규정 준수 요구 사항이 누락되었음을 깨달았습니다제품 소유자는 이 요구 사항이 현재 스프린트에서 완료되어야 하며 그렇지 않으면 조직이 페널티를 받게 될 것임을 팀에 상기시킵니다.

 

이 위험을 완화하기 위해 프로젝트 관리자는 무엇을 해야 합니까?

 

A. 프로젝트 후원자와 함께 문제를 검토하고 이 요구 사항을 완료하는 데 더 많은 시간을 요청하십시오.

B. 스프린트가 시작된 후에는 스프린트 백로그의 범위를 변경할 수 없으므로 영향 분석을 완료합니다.

C. 팀이 현재 스프린트에 전념하고 있으므로 다음 스프린트에 규정 준수 사용자 스토리를 포함합니다.

D. 현재 스프린트에 사용자 스토리를 추가하고 작업하도록 팀에 요청합니다.

 

정답이 B로 나오는데요, D가 더 적합하지 않나요?

 
첨부파일
2023-09-20

안녕하세요. ITPE입니다.
 

B는 정답이 될 수 없습니다. 

D는 부분적으로 틀립니다. 촉진자는 팀원들과 같이 조정합니다.

 

문제의 보기가 틀렸으면, D는 50%는 맞습니다. 


감사합니다.