덤프문제 질문(1) 입니다
오*수
|
2023-09-14

덤프문제입니다.

A project manager is replacing the knowledge-sharing platform of a project with a new web-based solution, ensuring that the system is aligned with a significant change in the organization's structure. The project charter was approved and the team is working on the detailed planning. The project management office (PMO) has provided detailed templates for all new projects to follow.

 

Which strategy should the project manager adopt for the project?

 

A. Align the project schedule with the PMO's change control process in collaboration with the PMO manager.

B. Develop a training and communications schedule with sufficient lead time in collaboration with the change agents.

C. Develop a communications management plan aligned with the new organizational structure in collaboration with the project sponsor.

D. Align the project schedule with the IT change control processes and tools in collaboration with the release manager.

 

프로젝트 관리자는 프로젝트의 지식 공유 플랫폼을 새로운 웹 기반 솔루션으로 교체하여 시스템이 조직 구조의 중요한 변화에 맞춰 조정되도록 합니다프로젝트 헌장이 승인되었으며 팀은 세부 계획을 수립 중입니다프로젝트 관리 사무소(PMO)는 앞으로 따라야 할 모든 새 프로젝트에 대한 자세한 템플릿을 제공했습니다.

 

프로젝트 관리자는 프로젝트를 위해 어떤 전략을 채택해야 합니까?

 

A. PMO 관리자와 협력하여 PMO의 변경 제어 프로세스에 맞춰 프로젝트 일정을 조정합니다.

B. 변화 주체와 협력하여 충분한 리드 타임을 두고 교육 및 커뮤니케이션 일정을 개발합니다.

C. 프로젝트 후원자와 협력하여 새로운 조직 구조에 맞춰 커뮤니케이션 관리 계획을 개발합니다.

D. 릴리스 관리자와 협력하여 IT 변경 제어 프로세스 및 도구에 맞게 프로젝트 일정을 조정합니다.

 

답은 라고하는데요, C가 정답아닐까요프로젝트 관리자는 프로젝트 후원자와 협력하여 커뮤니케이션 관리 계획이 프로젝트의 특정 요구 사항과 요구 사항을 충족하는지 확인할 수 있습니다.

 
첨부파일
2024-03-20

안녕하세요. ITPE입니다.

위 질문 문제들은 매월 모두 최근 기출문제에 반영 진행 중입니다.

 

문제 푸는 요령이 제일 중요합니다. 모의고사 앞의 5장 부분을 꼭 같이 보세요. 

 

답변 늦어서 죄송합니다. 

감사합니다.

첨부파일