특허가 있는 툴 사용관련 문제
정*주
|
2023-07-17
A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.

What should the project manager do to address this issued
  • a Schedule a meeting with critical stakeholders to review the issue and decide on the next steps
  • b Put the project on hold and release the resources until the issue is resolved
  • c Inform the product owner and log the issue in the risk register to monitor closely for next steps.
  • D Contact the company that owns the patent of the similar tool to compare the similarities and differences with the current project.

Freedump정답은 D로되어있습니다만, 

특허가 있는 업체에 연락해서 차이점을 본다는게 실제적으로는 어려울듯 하여 제 생각에는 정답이 A로 보이는데 어떤가요?

첨부파일
2023-07-19

안녕하세요. ITPE입니다.
 

이번 모의고사에 넣습니다만.

 

A도 답은 못됩닙니다~~~

Schedule a meeting → 애자일에서 사용하지 않는 문장입니다.

이슈 등 해결은 모두 일일 미팅을 원칙으로 합니다. 괜히 같은 장소에 있습니까?
 

이번 주 금요일 문제 올라오면 푸세요~ 답도 보시고요~~ 

감사합니다.