새로운 팀멤버 speed up ability문제
정*주
|
2023-07-13
A new team member has joined an agile project, replacing a team member who recently left. The project team needs the new team member to speed up their ability to contribute effectively to the project
What should the project manager do to help in this situation?
  • a Assign the new team member the same tasks that were assigned to the previous team member who they replaced
  • b Schedule knowledge transfer sessions and assign less complex tasks to the new team membercorrect
  • c Send technical documentation to the new team member and schedule training for the next iteration.
  • d Have the new team member complete all of the company’s mandatory training
  • 정답 B.

 

제가 선택한 답은 D였습니다.

문제 강의 주셨을때 비슷한 문제가 있었는데 그 문제에서는 필수교육과정부터 듣고 오게 하는 것이 맞다고 하였었는데,

B의 보기를 보면 지식전달세션을 가지고 덜 복잡한 Task부터 새로운 팀멤버에게 전달한다 인데, 이 문제의 답은 왜 B일까요? 

첨부파일
2023-07-13

안녕하세요. ITPE입니다.

b 지식 이전 세션을 예약하고 새 팀원에게 덜 복잡한 작업을 할당합니다.

→  새 팀원에게 덜 복잡한 작업을 할당합니다.(X). 앞 부분은 정답이지만, 뒤가 어벙함. 뒤가 맞으면, 전체 100개도 다 맞음. 


c 새 팀원에게 기술 문서를 보내고 다음 반복을 위한 교육 일정을 잡습니다.

- 정답 교육한다.  스피드 업이므로, 관련 문서를 보내고, 다음 스프린트 전에 교육한다. Gooooooooooooooooooooooooood!

 

정답 C. 

 