덤프문제 질문(3) 드립니다.
오*수
|
2023-09-14

덤프문제입니다.

A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements, the development of the product will take more time than expected. What should the project manager do?

 

A. Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project.

B. Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.

C. Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes.

D. Explain that distribution of important news can only be done using traceable communication methods.

 

프로젝트의 비즈니스 분석가는 엘리베이터에서 고객을 만나 요구 사항의 지속적인 변화로 인해 제품 개발에 예상보다 더 많은 시간이 걸릴 것이라고 말했습니다프로젝트 관리자는 무엇을 해야 합니까?

 

A. 프로젝트의 새로운 요구 사항과 더 긴 일정을 반영하기 위해 변경 제어 위원회(CCB)에 변경 요청을 제출합니다.

B. 프로젝트 일정과 관련된 모든 정보는 프로젝트 관리자가 전달해야 한다는 점을 프로젝트 팀과 고객에게 지적합니다.

C. 요구 사항 변경 사항을 처리하기 위해 더 많은 비즈니스 분석가를 할당할 수 있는지 알아보려면 리소스 관리 계획을 참조하세요.

D. 중요한 뉴스의 배포는 추적 가능한 의사소통 방법을 통해서만 이루어질 수 있음을 설명합니다.

 

답이 D로 나오는데요, A 나 어느것이 답인지 모르겠습니다.

 
첨부파일
2023-09-15

안녕하세요. ITPE입니다.

문제의 질문에, 상황 1줄이 2번째 줄에 빠졌습니다.

이 의사소통에 의해, 고객이 PM에게 불만을 제기했다(일정 등으로), 의사소통이 좀 상황이 복잡하다 등.

 

→ 의사소통 방법에 의해(애자일이든, 하이브리드 이든, 예측적방법론이든) 

그래서 D로 맞춰야 하는 문제입니다.

 

촉진자는 누구를 지적하지 않습니다. B도 답이 못됩니다. 

 

A는 위 문장에서, 예측적 개발이라는 상황을 만드는 용어 자체가 없습니다.  A도 답이 못됩니다. 

 

D도 위 1줄이 들어가면 답이 됩니다. 

 

문제 자체가 좀 어벙한 문제일 뿐입니다.  D로 만들려고 만든 문제일 뿐입니다. 

감사합니다.