 문제1) Development team members are located in three different time zones it is difficult to find a suitable time to hold the daily standup for all team members.


What should the project manager do?

1) Encourage frequent small team meetings with two or three team members.

2) Give up the daily standup and replace it with a daily report.

3) let the team members decide thenselves it they want to join the meeting.

4) Require all team members to join the daily standup regrardless of the meeting time.





문제 2) A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.


What should the project manager have done to avoid this?

1) Ensured the risk tolerance of the company was property updated.

2) Implemented the communications management plan properly.

3) Implemented the stakeholder engagement plan correctly.

4) Provided a proper risk response. 